Earthquake Engineering (3160621) MCQs

MCQs of Ductile Detailing

Showing 1 to 10 out of 15 Questions
1.

Which seismic code states the Indian standard guidelines for ductile detailing of RC structure subjected to Earthquake Forces?

(a)

IS : 13920-1993

(b)

IS : 13920-1995

(c)

IS : 13920-1998

(d)

IS : 13920-1999

Answer:

Option (a)

2.

Which seismic code states the Indian standard guidelines for ductile detailing of RC structure subjected to Earthquake Forces?

(a)

IS : 13920-1993

(b)

IS : 13925-1993

(c)

IS : 13910-1993

(d)

IS : 13930-1993

Answer:

Option (a)

3.

In Which earthquake zone Ductile Detailing required?

(a)

IV

(b)

V

(c)

III with Importance factor 1.

(d)

All of the above

Answer:

Option (d)

4.

_____________ Failure is occurred in the beam due to less steel provided on tension face.

(a)

Ductile

(b)

Brittle

(c)

Compression

(d)

Shear

Answer:

Option (a)

5.

For Ductile Detailing required in structure is located in seismic zone III and is more than ________ Storey High.

(a)

3

(b)

4

(c)

5

(d)

6

Answer:

Option (c)

6.

________ Minimum numbers of bars are provided throughout in beam top and bottom as per Indian standard 

(a)

2

(b)

3

(c)

4

(d)

5

Answer:

Option (a)

7.

Stirrups in RC beam provided to resist ______________

(a)

Vertical Shear

(b)

Protect Concrete from Bulging

(c)

Prevent Buckling of Longitudinal Bar

(d)

All of Above

Answer:

Option (d)

8.

The minimum diameter of the stirrups bar is provided in the beam more than 5m long.

(a)

6 mm

(b)

8 mm

(c)

10 mm

(d)

12 mm

Answer:

Option (b)

9.

The minimum diameter of stirrups bar is provided in the beam.

(a)

6 mm

(b)

8 mm

(c)

10 mm

(d)

12 mm

Answer:

Option (a)

10.

In stirrups both ends bent into ________ hook as per IS.

(a)

45°

(b)

75°

(c)

90°

(d)

135°

Answer:

Option (d)