1. |
Which seismic code states the Indian standard guidelines for ductile detailing of RC structure subjected to Earthquake Forces?
|
||||||||
Answer:
Option (a) |
2. |
Which seismic code states the Indian standard guidelines for ductile detailing of RC structure subjected to Earthquake Forces?
|
||||||||
Answer:
Option (a) |
3. |
In Which earthquake zone Ductile Detailing required?
|
||||||||
Answer:
Option (d) |
4. |
_____________ Failure is occurred in the beam due to less steel provided on tension face.
|
||||||||
Answer:
Option (a) |
5. |
For Ductile Detailing required in structure is located in seismic zone III and is more than ________ Storey High.
|
||||||||
Answer:
Option (c) |
6. |
________ Minimum numbers of bars are provided throughout in beam top and bottom as per Indian standard
|
||||||||
Answer:
Option (a) |
7. |
Stirrups in RC beam provided to resist ______________
|
||||||||
Answer:
Option (d) |
8. |
The minimum diameter of the stirrups bar is provided in the beam more than 5m long.
|
||||||||
Answer:
Option (b) |
9. |
The minimum diameter of stirrups bar is provided in the beam.
|
||||||||
Answer:
Option (a) |
10. |
In stirrups both ends bent into ________ hook as per IS.
|
||||||||
Answer:
Option (d) |