| 1. |
Rate analysis is a process of deriving rate of unit item from the cost of its _____________
|
||||||||
|
Answer:
Option (d) |
| 2. |
Which of the following cost is not included in Rate Analysis of an item _____________
|
||||||||
|
Answer:
Option (c) |
| 3. |
Usually contractor’s profit is taken ________ % for rate analysis of an item.
|
||||||||
|
Answer:
Option (a) |
| 4. |
Water charges are usually taken as ________ % for rate analysis of an item.
|
||||||||
|
Answer:
Option (c) |
| 5. |
Purpose of rate analysis is to ______________
|
||||||||
|
Answer:
Option (b) |
| 6. |
To fill the rate of an item in contract, Contractor needs to perform ____________.
|
||||||||
|
Answer:
Option (c) |
| 7. |
Which of the following can be prepared using rate analysis?
|
||||||||
|
Answer:
Option (b) |
| 8. |
The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is known as ________.
|
||||||||
|
Answer:
Option (d) |
| 9. |
Task work per day means ______ hours per day
|
||||||||
|
Answer:
Option (b) |
| 10. |
Which of the following factor affects task work of a labour?
|
||||||||
|
Answer:
Option (d) |