Home
Bachelor of Engineering
Computer Engineering
Semester-1
Semester-2
Semester-3
Semester-4
Semester-5
Semester-6
Semester-7
Semester-8
Civil Engineering
Semester-1
Semester-2
Semester-3
Semester-4
Semester-5
Semester-6
Semester-7
Semester-8
Electrical Engineering
Semester-1
Semester-2
Semester-3
Semester-4
Semester-5
Semester-6
Semester-7
Semester-8
Mechanical Engineering
Semester-1
Semester-2
Semester-3
Semester-4
Semester-5
Semester-6
Semester-7
Semester-8
Diploma Engineering
Computer Engineering
Semester-3
Semester-4
Semester-5
Semester-6
Civil Engineering
Semester-3
Semester-4
Semester-5
Semester-6
Electrical Engineering
Semester-3
Semester-4
Semester-5
Semester-6
Mechanical Engineering
Semester-3
Semester-4
Semester-5
Semester-6
About
Contact
Construction Management (2180611)
MCQ
MCQs of Linear Programming in Construction Management
Next
MCQ No - 1
Liner programming was initially developed by ____________ for military operations.
(A)
George Dantzig
(B)
Juran Safinag
(C)
Henery Gantt
(D)
D.R. Fulkerson
Answer
A
MCQ No - 2
Liner programming solves problem by ________
(A)
By dividing work in manageable part
(B)
By mathematical conversion into linear equation
(C)
By identification of constrains and objectives
(D)
By converting into partial differential equation
Answer
B
MCQ No - 3
A brick manufacturer can run furnace for 8 hours and have three options of different size and its variable production time, find out maximum profitable option. 1. Size X – Production Time 20mins. – Profit 3Rs. 2. Size Y – Production Time 10 mins. – Profit 2.5Rs. 3. Size Z – Production Time 15 mins. – Profit 3Rs.
(A)
Size X
(B)
Size Y
(C)
Size Z
(D)
Size X and Z
Answer
B
MCQ No - 4
When it is feasible to use graphical method of liner programming?
(A)
When constrains are know
(B)
When resources are limited
(C)
When quality is important
(D)
When there is only two variables
Answer
D
MCQ No - 5
Arrange following steps of Simplex method of liner programming in appropriate sequence: 1. Setting up initial simplex solution 2. Generalizing the objective function and constrain 3. Identifying mathematical model 4. Converting the constrains into equation
(A)
1-2-4-3
(B)
1-2-3-4
(C)
3-4-1-2
(D)
4-3-1-2
Answer
C
Construction Management(2180611)
1. Introduction
2. Project Organization
3. Construction Economics
4. Construction Planning
5. Project scheduling and Resource leveling
6. Construction Equipment Management
7. Construction Accounts Management
8. Construction Material Management
9. Construction Project Cost and Cost and Value Management
10. Construction Quality Management
11. Construction Safety Management
12. Linear Programming in Construction Management
13. Factors for Success of a Construction Project
Please Wait...