Construction Management (2180611) MCQ

MCQs of Introduction

MCQ No - 1

Which of the following is not a phase of construction project?

(A) Tendering
(B) Estimation
(C) Briefing
(D) Commissioning

B
MCQ No - 2

Which of the following is a phase of construction project?

(A) Briefing
(B) Designing
(C) Construction
(D) All of the above

D
MCQ No - 3

Feasibility report is prepared in which phase of construction project?

(A) Commissioning
(B) Construction
(C) Tendering
(D) Briefing

D
MCQ No - 4

Estimation of quantities is done in which phase of construction project?

(A) Construction
(B) Briefing
(C) Designing
(D) Tendering

C
MCQ No - 5

Notice inviting tender is published in which phase of construction project?

(A) Briefing
(B) Designing
(C) Tendering
(D) Construction

C