MCQ No - 1

Which of the following is true in case of cost of building project?

(A) Total Cost = Material cost (60%) + Labour Cost (25%) + POL, Overhead and Profit (15%)
(B) Total Cost = Material cost (70%) + Labour Cost (25%) + POL, Overhead and Profit (5%)
(C) Total Cost = Material cost (45%) + Labour Cost (45%) + POL, Overhead and Profit (10%)
(D) Total Cost = Material cost (25%) + Labour Cost (60%) + POL, Overhead and Profit (15%)

A
MCQ No - 2

What are the main objective of material management?

(A) To minimize the material cost
(B) To procure and provide desired quality materials when required.
(C) To reduce the transportation cost of materials
(D) All of the above

D
MCQ No - 3

Which of the following is not a function of material management?

(A) Material Planning
(B) Material Production
(C) Procurement
(D) Materials accounting

B
MCQ No - 4

Which of the following is a function of material management?

(A) Transportation
(B) Computerization
(C) Source development
(D) All of the above

D
MCQ No - 5

Material wastage analysis can be done through which function of material management?

(A) Material Planning
(B) Material Production
(C) Materials accounting
(D) Procurement