Construction Management (2180611) MCQ

MCQs of Construction Planning

MCQ No - 1

Which one of the following represents an activity

(A) Excavation for foundation
(B) Curing of concrete
(C) Setting of question paper
(D) All the above

D
MCQ No - 2

Pick up the incorrect statement from the following

(A) An activity of a project is denoted by an arrow on the net work
(B) The tail of the arrow indicates the start of the activity
(C) The arrows are drawn to scale from left to right
(D) Each activity consumes a given time

C
MCQ No - 3

Pick up the PERT event from the following

(A) Digging of foundation started
(B) Digging of foundation completed
(C) Laying of concrete started
(D) All the above

D
MCQ No - 4

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

(A) EF = ES + D
(B) LS = LF - D
(C) D = EF - ES
(D) All the above

D
MCQ No - 5

The performance of a specific task in CPM, is known

(A) Dummy
(B) Event
(C) Activity
(D) Contract

C