Construction Management (2180611) MCQ

MCQs of Construction Equipment Management

MCQ No - 1

Which method can be used for economic analysis of construction equipment?

(A) Breakeven Analysis
(B) Sensitivity Analysis
(C) Both A and B
(D) None of the above

C
MCQ No - 2

Which method of economic analysis considers different variables for evaluation of alternative?

(A) Breakeven Analysis
(B) Sensitivity Analysis
(C) Both A and B
(D) None of the above

B
MCQ No - 3

Which variables are considered while evaluation of alternatives using sensitivity analysis method?

(A) Initial Cost
(B) Service Life
(C) Interest Rate
(D) All of the above

D
MCQ No - 4

If minor changes in variable alters the outcome of economic analysis then such variable is called ____________.

(A) Less sensitive variable
(B) Highly sensitive variable
(C) Insensitive variable
(D) Complex sensitive variable

B
MCQ No - 5

When two variables are changing at same time than such problems can be solved by __________ form of Sensitivity analysis.

(A) Spider web diagram
(B) Scenario Analysis
(C) Family of curves
(D) All of the above

C