The objective of network analysis is to
minimize total project duration
minimize total project cost
minimize production delays, interruption, and conflicts
all of these
Answer
Network models have advantage in terms of project
planning
scheduling
controlling
The other term commonly used for activity slack time is
total float
free float
independent float
Generally the PERT technique deals with the project of
repetitive nature
non-repetitive nature
deterministic nature
none of these
If an activity has zero slack, it implies that
it lies on the critical path
it is a dummy activity
the project is progressing well
None of these