| 1. |
The objective of network analysis is to
|
||||||||
|
Answer:
Option (a) |
| 2. |
Network models have advantage in terms of project
|
||||||||
|
Answer:
Option (d) |
| 3. |
The other term commonly used for activity slack time is
|
||||||||
|
Answer:
Option (d) |
| 4. |
Generally the PERT technique deals with the project of
|
||||||||
|
Answer:
Option (d) |
| 5. |
If an activity has zero slack, it implies that
|
||||||||
|
Answer:
Option (a) |
| 6. |
A dummy activity is used in the network diagram when
|
||||||||
|
Answer:
Option (a) |
| 7. |
While drawing the network diagram, for each activity project, we should look
|
||||||||
|
Answer:
Option (d) |
| 8. |
In the PERT network, each activity time assumes a Beta distribution because
|
||||||||
|
Answer:
Option (a) |
| 9. |
Float or slack analysis is useful for
|
||||||||
|
Answer:
Option (a) |
| 10. |
The activity that can be delayed without affecting the execution of the immediate succeeding activity is determined by
|
||||||||
|
Answer:
Option (b) |