| 11. |
In time cost-trade-off function analysis
|
||||||||
|
Answer:
Option (a) |
| 12. |
Activity-on-Arrow (AOA) diagram is preferred over Activity-on- Node (AON) diagram because
|
||||||||
|
Answer:
Option (b) |
| 13. |
The slack for an activity is equal to
|
||||||||
|
Answer:
Option (d) |
| 14. |
In PERT the span of time between the optimistic and pessimistic time estimates of activity is
|
||||||||
|
Answer:
Option (b) |
| 15. |
The critical path satisfies the condition that
|
||||||||
|
Answer:
Option (a) |