| 11. |
The surcharge storage in a dam reservoir is the volume of water stored
|
||||||||
|
Answer:
Option (c) |
| 12. |
The useful storage in a dam reservoir is the volume of water stored
|
||||||||
|
Answer:
Option (b) |
| 13. |
The dead storage in a dam reservoir is the available volume for collection of silt and sediment between
|
||||||||
|
Answer:
Option (a) |
| 14. |
Bank storage in a dam reservoir
|
||||||||
|
Answer:
Option (a) |
| 15. |
The maximum level to which the water rises during the worst design flood is known as
|
||||||||
|
Answer:
Option (a) |
| 16. |
which of the following formula can be used to determine the storage when three consecutive sections at equal height are taken?
|
||||||||
|
Answer:
Option (a) |
| 17. |
Average yield of a storage reservoir is the arithmetic average of its
|
||||||||
|
Answer:
Option (c) |
| 18. |
While planning a water supply reservoir as compared to an irrigation reservoir the design yield may be kept
|
||||||||
|
Answer:
Option (b) |
| 19. |
Yield of a reservoir represents
|
||||||||
|
Answer:
Option (c) |
| 20. |
Design yield of a storage reservoir is kept
|
||||||||
|
Answer:
Option (b) |