11.

In which type of contract among listed below has the highest chances of ring formation?

(a)

Turn Key Contract

(b)

Item Rate Contract

(c)

Percentage Rate Contract

(d)

BOT Contract

Answer:

Option (c)

12.

In which type of contract, bidders are allowed to quote rate in percentage of tender amount?

(a)

Iteam Rate Contract

(b)

Percentage Rate Contract

(c)

Measured Contract

(d)

BOT Contract

Answer:

Option (b)

13.

In which type of contract there is a possibility of unbalanced tender ?

(a)

Percentage Rate Contract

(b)

Lump-Sum Contract

(c)

Item Rate Contract

(d)

Turn Key Contract

Answer:

Option (c)

14.

In which type of contract possiblity of ring formation can be avoided?

(a)

Percentage Rate Contract

(b)

Material Supply Contract

(c)

Item Rate Contract

(d)

Labour Contract

Answer:

Option (c)

15.

In which type of contract bidders are allowed to quote rate of individual items?

(a)

BOT Contract

(b)

Item Rate Contract

(c)

Material supply Contract

(d)

Piece work agreement

Answer:

Option (b)

16.

Which of this is not a type of Cost Plus Contract ?

(a)

Cost Plus Percentage Rate Contract

(b)

Target Contract

(c)

Piece work agreement

(d)

Cost plus sliding fee contract

Answer:

Option (c)

17.

Which of this is not a type of contract ?

(a)

Item Rate Contract

(b)

Open Contract

(c)

Percentage Rate Contract

(d)

Lump-Sum Contract

Answer:

Option (b)

18.

Which of the following is not a type of Integrated Contract?

(a)

Lump Sum Contract

(b)

Design - Build Contract

(c)

Turn Key Contract

(d)

BOT Contract

Answer:

Option (a)

19.

Which of these is not a separated contract?

(a)

Lump sum contract

(b)

BOT Contract

(c)

Item Rate Contract

(d)

Cost Plus Contract

Answer:

Option (b)

20.

Which of these is not a type of Cost Plus Contract?

(a)

Cost Plus Fixed Fee Contract

(b)

Cost Plus Percentage Rate Contract

(c)

Target Contract

(d)

Turn Key Contract

Answer:

Option (d)