Contracts Management (3160614) MCQs

MCQs of Tendering

Showing 21 to 30 out of 56 Questions
21.

Pre-qualification of contractor is a process that is done ________ to actual tendering process

(a)

After

(b)

Before

(c)

Simultaneously

(d)

Repetitively

Answer:

Option (b)

22.

Which of the following documents are supplied by contractor during pre-qualification process?

(a)

Experience Related Documents

(b)

Financial Capacity Documents

(c)

Technical Staff and Equipments Ownership Document

(d)

All of the above

Answer:

Option (d)

23.

In joint venture maximum ______ number of contractors can jointly bid for the work

(a)

4

(b)

5

(c)

3

(d)

2

Answer:

Option (c)

24.

To be eligible for bidding a contractor need to achieve minimum ______ points overall in pre-qualification process.

(a)

35

(b)

50

(c)

70

(d)

60

Answer:

Option (c)

25.

A notice inviting vendors to participate in pre-qualification process is formally called as ________

(a)

Request for Proposal (FRP)

(b)

Request for Quotation (RFQ)

(c)

Expression of Interest (EOI)

(d)

None of the above

Answer:

Option (c)

26.

When buyer has a requirment of solution and its prices they will invite ________ from perspective vendors.

(a)

Expression of Interest (EOI)

(b)

Request for Proposal (RFP)

(c)

Request for Quotation (RFQ)

(d)

Tender Documents

Answer:

Option (b)

27.

When owner has a requirment with specific solution he/she will request ________ from supplier.

(a)

Request for Quotation (RFQ)

(b)

Request for Proposal (RFP)

(c)

Expression of Interest (EOI)

(d)

Tender Documents

Answer:

Option (a)

28.

For submission of tender ______ number of envelopes are prepared.

(a)

2

(b)

4

(c)

5

(d)

3

Answer:

Option (b)

29.

Which of the following details is not included in envelop no.2 of technical document?

(a)

Details of similar work experience

(b)

Last three income tax returns

(c)

Price Bid

(d)

Covering letter

Answer:

Option (c)

30.

Which of the following document is included in envelop 2 of technical bid?

(a)

Solvency Certificate

(b)

Details of plant and machinery

(c)

Details of Technical Staff employed

(d)

All of the above

Answer:

Option (d)

Showing 21 to 30 out of 56 Questions