Contracts Management (3160614) MCQs

MCQs of Tendering

Showing 41 to 50 out of 56 Questions
41.

Which of the following is not a reason for rejection of lowest tender?

(a)

When tender is not submitted in prescribed format

(b)

When there is any unreasonable condition

(c)

When contractor is having more experience then required

(d)

When tender amount is exceeding senctioned amount

Answer:

Option (c)

42.

In which of the following circumstances the lowest tender can be rejected?

(a)

Adequate competition not received

(b)

Fair rates are not received

(c)

Signature of bidder is missing

(d)

all of the above

Answer:

Option (d)

43.

To enter into an agreement ________ officer is authorized to sign on behalf of governor of the state.

(a)

Superintending Officer

(b)

Executive Engineer

(c)

Divisional Accountant

(d)

Engineer in Charge

Answer:

Option (b)

44.

Which documents are used as reference while drafting contract agreement?

(a)

Notice inviting tender

(b)

Tender submitted by contractor

(c)

Latter of acceptance issued to contractor

(d)

All of the above

Answer:

Option (d)

45.

If tender is accepted by executive engineer _______ original copies of tender are prepared.

(a)

3

(b)

4

(c)

2

(d)

5

Answer:

Option (a)

46.

If tender is accepted by superintended engineer _______ copies of tender are prepared.

(a)

3

(b)

4

(c)

5

(d)

2

Answer:

Option (b)

47.

Changes in the contract deed can be made by ________ only

(a)

Chief Engineer

(b)

Superintendent Engineer

(c)

Executive Engineer

(d)

Representative of Contractor

Answer:

Option (c)

48.

If any extra items are to be executed as a result of change in design, rate for such items are derived from ________.

(a)

Contractor's Price List

(b)

Market Rate

(c)

Provisional Rate

(d)

Schedule of Rates (S.O.R)

Answer:

Option (d)

49.

In which condition the contractor is eligible for extension of time?

(a)

If owner fails to handover site

(b)

If owner fails to furnish drawings

(c)

If owner fails to pay on time

(d)

All of the above

Answer:

Option (d)

50.

In which case contractor is not eligible for extension in time?

(a)

Owner failed to pay contractor on time

(b)

Engineer in charge fails to certify the work done within timelimit

(c)

Work not done due to monsoon season

(d)

None of the above

Answer:

Option (c)

Showing 41 to 50 out of 56 Questions