Contracts Management (3160614) MCQs

MCQs of Tendering

Showing 51 to 56 out of 56 Questions
51.

Damages caused due to delay in work are termed as ________.

(a)

Liquidated Damages

(b)

Unliquidated Damages

(c)

Direct Damages

(d)

Tangible Damages

Answer:

Option (a)

52.

Event in which neither government nor the contractor can be held responsible for delay are termed as ________

(a)

Liquidated Damages

(b)

Force Majeure

(c)

Indirect Damages

(d)

Delay due to negligence

Answer:

Option (b)

53.

Force Majeure can be ________.

(a)

Act of God

(b)

Fire or explosion

(c)

Wars or hostalities

(d)

All of the above

Answer:

Option (d)

54.

Force Majeure can not be ________

(a)

Restraints of government authorities

(b)

Blockades or Public disorders

(c)

Rainy Season

(d)

Quarantine restrictions

Answer:

Option (c)

55.

In the event of Force Majeure _______ can be done.

(a)

Extension in time limit

(b)

Temporary Suspension of work

(c)

Termination of Contract

(d)

All of the above

Answer:

Option (d)

56.

Person acting as representative of government on site is known as ________.

(a)

Engineer in charge

(b)

Officer in charge

(c)

Supervisor

(d)

Subdivisional Accountant

Answer:

Option (a)

Showing 51 to 56 out of 56 Questions