1.

Which document in contract sets out responsibilities and obligation of parties to the contract?

(a)

Tender Notice

(b)

Specifications

(c)

General Conditions of Contract

(d)

None of the above

Answer:

Option (c)

2.

Why in most cases only the general condition of contracts are being used frequently?

(a)

It is easy to prepare documents

(b)

It has been tried and tested in courts

(c)

It is mandatory to use the same

(d)

All of the above

Answer:

Option (b)

3.

In India for government work which conditions are mostly used?

(a)

CPWD conditions of contract

(b)

Indian Contract Act

(c)

FIDIC conditions of contract

(d)

All of the above

Answer:

Option (a)

4.

In India there is a growing demand for ________ conditions of contract for private projects

(a)

CPWD

(b)

FIDIC

(c)

Indian Contract Act

(d)

Indian Construction Act

Answer:

Option (b)

5.

For making contract more suitable to work certain amendments or additions are done in general conditions of contract which is called as _______

(a)

CPWD Contract Changes

(b)

FIDIC Contractual Changes

(c)

Special Conditions of Contract

(d)

None of the above

Answer:

Option (c)

6.

Special conditions of contract can be related to ________.

(a)

Materials provided by owner

(b)

Site visits

(c)

Mobilization Advance

(d)

All of the above

Answer:

Option (d)

7.

Special Condition of contract can not be related to ________

(a)

Start date of construction

(b)

Delay in payments related conditions

(c)

Requirement of various progress reports

(d)

All of the above

Answer:

Option (b)

8.

Which of the following is a condition of contract?

(a)

Security Deposit

(b)

Compensation for Delay

(c)

Extension in Time Limit

(d)

All of the above

Answer:

Option (d)

9.

In which condition of contract time duration for certifying the contractor's running account bill is specified?

(a)

Extension of time limit

(b)

Payment on certificate

(c)

Compensation for delay

(d)

Extra items and its payments

Answer:

Option (b)

10.

In which condition of contract amount and format of performance guarantee is specified?

(a)

Completion Certificate

(b)

Payment on Certificate

(c)

Security Deposit

(d)

Inferior Materials and Workmanship

Answer:

Option (c)