Contracts Management (3160614) MCQs

MCQs of Conditions of Contract

Showing 11 to 20 out of 25 Questions
11.

As per the condition of work at night and holidays ________

(a)

Work between sunset and sunrise is not permitted

(b)

Work on public holidays is not permitted

(c)

Work on holidays and night can be carried our with prior permission

(d)

All of the above

Answer:

Option (d)

12.

Which contract condition empowers engineer in charge to order for rework of certain parts or removal of certain materials from site?

(a)

Work at night and holiday condition

(b)

Payment on certificate condition

(c)

Inferior materials and workmanship condition

(d)

Departmental materials condition

Answer:

Option (c)

13.

Which condtions specifies use of materials provided by owner?

(a)

Inferior materials and workmanship condition

(b)

Departmental materials condition

(c)

Extra items and its payment condition

(d)

Measurement and Payment to contractor

Answer:

Option (b)

14.

Which contract conditions specifies rate of extra work to be done by contractor?

(a)

Measurement and payments to contractor condition

(b)

Extra items and its payments conditions

(c)

Payment on certificate

(d)

Subleting

Answer:

Option (b)

15.

Which contract condition prohibits or allows contractor to transfer entire work to other person?

(a)

Breach of contract

(b)

Additions and Alterations

(c)

Subletting

(d)

Compensation for Delay

Answer:

Option (c)

16.

Which contract condition makes contractor liable to do any extra work arising while execution of contract?

(a)

Subleting

(b)

Measurement and Payment to contractor

(c)

Labour Laws

(d)

Additions and Alteration

Answer:

Option (d)

17.

Which contract condition specifies responsibilities of contractor towards labours employed at site?

(a)

Clerk of works

(b)

Labour Laws

(c)

Compensation in case of bad work

(d)

Supervision of work

Answer:

Option (b)

18.

Which contract condition appoints goverment's representative on site and his duties?

(a)

Labour Laws

(b)

Supervision of Work

(c)

Cleark of Works

(d)

Subletting

Answer:

Option (c)

19.

In the event of requirement fo extension in time limit a contracor needs to intimate department within ______ days of delay or prior to project completion date.

(a)

15

(b)

20

(c)

30

(d)

60

Answer:

Option (c)

20.

For the settlement of runnig account bill and final bill owner or department usually have ______ and _____ days time respectively.

(a)

15, 30

(b)

20, 45

(c)

10, 30

(d)

30, 60

Answer:

Option (d)

Showing 11 to 20 out of 25 Questions