21. |
As per IRC:65, from the calculated capacity of a weaving section of a rotary intersection 5% is deducted if the entry angle is between ________ and ________.
|
||||||||
Answer:
Option (d) |
22. |
As per IRC:65, from the calculated capacity of a weaving section of a rotary intersection 2.5% is deducted if the entry angle is between ________ and ________.
|
||||||||
Answer:
Option (c) |
23. |
As per IRC:65, from the calculated capacity of a weaving section of a rotary intersection______ is deducted if 60o<exit angle<75o
|
||||||||
Answer:
Option (c) |
24. |
Deduct 1/6th of the calculated capacity of the weaving section if pedestrian flow at the exit from the rotary exceeds __________.
|
||||||||
Answer:
Option (a) |
25. |
The recommended minimum length of the weaving section of a rotary intersection should be _______ times the width of the weaving section.
|
||||||||
Answer:
Option (d) |
26. |
As per IRC:65, the proportion of weaving traffic to total traffic in the weaving section of a rotary intersection should be in the range __________.
|
||||||||
Answer:
Option (c) |
27. |
Which type of conflict occurs in a rotary?
|
||||||||
Answer:
Option (d) |
28. |
Which one of the following traffic signal system is useful when there is continuous operation of a group of vehicles along the main road?
|
||||||||
Answer:
Option (b) |
29. |
The most efficient system of signal coordination along a street with intersecting roads is ___________.
|
||||||||
Answer:
Option (b) |
30. |
The rate of speed of a platoon of vehicles travelling between any two consecutive intersections may vary and the same is scheduled with their respective "GO" indications, across the street, in which of the following systems?
|
||||||||