11. |
Time and progress chart of a construction, is also known as
|
||||||||
Answer:
Option (d) |
12. |
Critical Path Network helps an engineer
|
||||||||
Answer:
Option (d) |
13. |
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
|
||||||||
Answer:
Option (c) |
14. |
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
|
||||||||
Answer:
Option (c) |
15. |
The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
|
||||||||
Answer:
Option (c) |
16. |
Henry Gantt developed Bar charts for planning and scheduling of projects in
|
||||||||
Answer:
Option (b) |
17. |
The difference between the time avail-to do a job and the time required to do the job, is known as
|
||||||||
Answer:
Option (b) |
18. |
Critical path method
|
||||||||
Answer:
Option (d) |
19. |
CPM is
|
||||||||
Answer:
Option (d) |
20. |
Critical path lies along the activities having total float
|
||||||||
Answer:
Option (c) |