21. |
Volume of 1 bag (50kg) of cement is ________ m3
|
||||||||
Answer:
Option (c) |
22. |
What will be volume of dry mortart for plaster work, if volume of wet mortar is 10m3?
|
||||||||
Answer:
Option (b) |
23. |
When water is added to dry mix of concrete its volume shrinks by ________ %
|
||||||||
Answer:
Option (d) |
24. |
For 1 : 3 proportion of mortar for plaster work parts of sand will be ________ .
|
||||||||
Answer:
Option (c) |
25. |
For M20 grade of concrete, ______ parts of cement is required.
|
||||||||
Answer:
Option (a) |
26. |
For M15 grade of concrete total part of concrete is ________.
|
||||||||
Answer:
Option (b) |
27. |
The quantity of cement required for RCC (1:2:4) for 10m3 is ________.
|
||||||||
Answer:
Option (d) |
28. |
The rate of an item of work depends on
|
||||||||
Answer:
Option (d) |