| 11. |
Bentonite slurry used in the construction of
|
||||||||
|
Answer:
Option (c) |
| 12. |
Where the retaining wall needs to allow high amounts of water to pass through it, as in the case of riverbank stabilization which one of following used
|
||||||||
|
Answer:
Option (b) |
| 13. |
Design of gravity wall aims to
|
||||||||
|
Answer:
Option (d) |
| 14. |
A minimum factor of safety against sliding is recommended as
|
||||||||
|
Answer:
Option (c) |
| 15. |
Factor of safety against bearing pressure is recommended as
|
||||||||
|
Answer:
Option (b) |
| 16. |
If the temporary Excavation is made in sand, the walls of the excavation must be supported during the construction of the building by a system
|
||||||||
|
Answer:
Option (b) |
| 17. |
pressure diagram for a braced cut in dry or moist sand with a pressure
|
||||||||
|
Answer:
Option (a) |
| 18. |
Weep holes provided into retaining wall for the purpose of
|
||||||||
|
Answer:
Option (a) |
| 19. |
as compared to the cantilever sheet pile, the required depth of anchored sheet pile below the dredge line is
|
||||||||
|
Answer:
Option (b) |
| 20. |
an anchor sheet pile driven to a shallow depth will have
|
||||||||
|
Answer:
Option (a) |