11. |
Bentonite slurry used in the construction of
|
||||||||
Answer:
Option (c) |
12. |
Where the retaining wall needs to allow high amounts of water to pass through it, as in the case of riverbank stabilization which one of following used
|
||||||||
Answer:
Option (b) |
13. |
Design of gravity wall aims to
|
||||||||
Answer:
Option (d) |
14. |
A minimum factor of safety against sliding is recommended as
|
||||||||
Answer:
Option (c) |
15. |
Factor of safety against bearing pressure is recommended as
|
||||||||
Answer:
Option (b) |
16. |
If the temporary Excavation is made in sand, the walls of the excavation must be supported during the construction of the building by a system
|
||||||||
Answer:
Option (b) |
17. |
pressure diagram for a braced cut in dry or moist sand with a pressure
|
||||||||
Answer:
Option (a) |
18. |
Weep holes provided into retaining wall for the purpose of
|
||||||||
Answer:
Option (a) |
19. |
as compared to the cantilever sheet pile, the required depth of anchored sheet pile below the dredge line is
|
||||||||
Answer:
Option (b) |
20. |
an anchor sheet pile driven to a shallow depth will have
|
||||||||
Answer:
Option (a) |