Construction Management (2180611) MCQs

MCQs of Introduction

Showing 1 to 10 out of 15 Questions
1.
Which of the following is not a phase of construction project?
(a) Tendering
(b) Estimation
(c) Briefing
(d) Commissioning
Answer:

Option (b)

2.
Which of the following is a phase of construction project?
(a) Briefing
(b) Designing
(c) Construction
(d) All of the above
Answer:

Option (d)

3.
Feasibility report is prepared in which phase of construction project?
(a) Commissioning
(b) Construction
(c) Tendering
(d) Briefing
Answer:

Option (d)

4.
Estimation of quantities is done in which phase of construction project?
(a) Construction
(b) Briefing
(c) Designing
(d) Tendering
Answer:

Option (c)

5.
Notice inviting tender is published in which phase of construction project?
(a) Briefing
(b) Designing
(c) Tendering
(d) Construction
Answer:

Option (c)

6.
Schedule for operation, maintenance and repair of building is prepared in which phase of construction project?
(a) Construction
(b) Designing
(c) Tendering
(d) Commissioning
Answer:

Option (d)

7.
Which of the following is an objective of construction management?
(a) Completing the work within estimated budget and time
(b) To complete the work as per specification
(c) To control quality of workmanship
(d) All of the above
Answer:

Option (d)

8.
In which of the following situation construction management is not needed?
(a) To co-ordinate between different agencies
(b) To bid for the tender
(c) To achieve speed and economy in construction
(d) To control quality of materials and workmanship
Answer:

Option (b)

9.
Which of the following is not a function of construction management?
(a) Planning
(b) Scheduling
(c) Staffing
(d) Tendering
Answer:

Option (d)

10.
Which of the following is a function of construction management?
(a) Communicating
(b) Designing
(c) Tendering
(d) Cooperating
Answer:

Option (a)

Showing 1 to 10 out of 15 Questions