21. |
Product Backlog should be ordered on the basis of _____________________.
|
||||||||
Answer:
Option (a) |
22. |
In an Agile environment, what is the main responsibility of a tester?
|
||||||||
Answer:
Option (d) |
23. |
When is a Sprint Retrospective ceremony performed?
|
||||||||
Answer:
Option (a) |
24. |
What should a development team do during a Sprint Planning meeting when they have realized that they have selected more than the items they can complete in a Sprint?
|
||||||||
Answer:
Option (d) |
25. |
BurnDown Chart represents ________________.
|
||||||||
Answer:
Option (b) |
26. |
In Scrum, when is a Sprint Over?
|
||||||||
Answer:
Option (d) |
27. |
What is done during a Sprint Review Meeting?
|
||||||||
Answer:
Option (c) |
28. |
What is a Sprint Review?
|
||||||||
Answer:
Option (a) |
29. |
What do we mean by a cross-functional Development Team?
|
||||||||
Answer:
Option (d) |