31. |
__________is not considered as a risk in project management.
|
||||||||
Answer:
Option (c) |
32. |
__________is/are main parameters that you should use when computing the costs of a software development project.
|
||||||||
Answer:
Option (d) |
33. |
The project planner examines the statement of scope and extracts all important software functions which is known as __________.
|
||||||||
Answer:
Option (b) |
34. |
__________ is used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right.
|
||||||||
Answer:
Option (b) |
35. |
__________ is related to the overall functionality of the delivered software.
|
||||||||
Answer:
Option (a) |
36. |
__________uses empirically derived formulas to predict effort as a function of LOC or FP.
|
||||||||
Answer:
Option (d) |
37. |
COCOMO stands for __________.
|
||||||||
Answer:
Option (a) |
38. |
__________version of COCOMO states that once requirements have been stabilized, the basic software architecture has been established.
|
||||||||
Answer:
Option (a) |
39. |
__________ is not a size measure for software product.
|
||||||||
Answer:
Option (d) |
40. |
COCOMO was developed initially by __________.
|
||||||||
Answer:
Option (c) |