401. |
A power plant has a maximum demand of 15 MW. Load factor is 50% and the plant factor is 40%. The operating reserve is
|
||||||||
Answer:
Option (b) |
402. |
Which of the following relations holds good?
|
||||||||
Answer:
Option (d) |
403. |
Two areas A and B have equal connected loads. However load diversity in area A is more than in area B.Then
|
||||||||
Answer:
Option (c) |
404. |
A large diversity factor of the load in a power system
|
||||||||
Answer:
Option (a) |
405. |
As the load factor of power plant increases, the cost for kWh of the energy generated
|
||||||||
Answer:
Option (b) |
406. |
In order to have a lower cost of electrical energy generation
|
||||||||
Answer:
Option (d) |
407. |
In a power station, the cost of generation of power reduces most effectively when
|
||||||||
Answer:
Option (b) |
408. |
A region has a maximum demand of 500 MW at a load factor of 50%. The load duration curve can be assumed to be a triangular.Utility has to meet this load by setting up a generating system which has partly hydro and partly thermal. The costs are as under.
Hydro plant : Rs.600 per kW per annum plus 3p per kWh Thermal plant : Rs.300 per kW per annum plus 13p per kWh The respective capacity of hydro and thermal power plants for minimum cost are
|
||||||||
Answer:
Option (a) |
409. |
A region has a maximum demand of 500 MW at a load factor of 50%. The load duration curve can be assumed to be a triangular.Utility has to meet this load by setting up a generating system which has partly hydro and partly thermal. The costs are as under.
Hydro plant : Rs.600 per kW per annum plus 3p per kWh Thermal plant : Rs.300 per kW per annum plus 13p per kWh The energy generated annually by hydro and thermal power plant for minimum cost are
|
||||||||
Answer:
Option (a) |
410. |
Flat rate tariff can be charged on the basis of
|
||||||||
Answer:
Option (b) |