91. |
11 kV cable after installation should be checked for short duration at a voltage of
|
||||||||
Answer:
Option (c) |
92. |
The force which are most likely to occur in underground cables are
|
||||||||
Answer:
Option (d) |
93. |
The cause of damage to the lead sheath of cables are
|
||||||||
Answer:
Option (d) |
94. |
Loop test in cable cannot locate the
|
||||||||
Answer:
Option (a) |
95. |
In a loop test performed for localizing the earth fault in cable, fault resistance
|
||||||||
Answer:
Option (b) |
96. |
Varley loop tests are performed over Murray loop test because
|
||||||||
Answer:
Option (c) |
97. |
Open circuit test in a cable can be located by
|
||||||||
Answer:
Option (b) |
98. |
At NTP the breakdown strength of air is
|
||||||||
Answer:
Option (b) |
99. |
The leakage resistance of a 50 km long cable is 1 MΩ. For a 100 km long cable it will be
|
||||||||
Answer:
Option (d) |
100. |
Sheaths are used in cables to
|
||||||||
Answer:
Option (b) |