1.
__________ is the process of assuring that all systems and components of a major piece of equipment, a process, a building or similar are designed, installed and tested according to the operational requirements of the owner or final client.
(a) Testing
(b) Installation
(c) Commissioning
(d) Storage
Answer:

Option (c)

2.
__________ is the process of evaluating a system or its component(s) with the intent to find whether it satisfies the specified requirements or not.
(a) Testing
(b) Installation
(c) Commissioning
(d) Storage
Answer:

Option (a)

3.
_____________ standard specified General Requirements for Type, Routine and Special Tests for transformer.
(a) IS 2026
(b) IS 4029:2010
(c) IS 9320:1979
(d) IS 7132:1973
Answer:

Option (a)

4.
According to IS 2026: Part_1, Transformer tests shall be made at any ambient temperature between __________ °C and with cooling water (if required) at any temperature not exceeding _________ °C.
(a) 10-50, 30
(b) 20-40, 25
(c) 25-55, 45
(d) 10-30, 30
Answer:

Option (a)

5.
According to IS 2026: Part_1, Transformer tests shall be made at the __________, unless otherwise agreed between the manufacturer and the purchaser.
(a) consumer's works
(b) manufacturer’s works
(c) Third-party's place
(d) All of these
Answer:

Option (b)

6.
According to IS 2026: Part_1, If required than test results are to be corrected to a reference temperature __________ °C for oil-immersed transformers.
(a) 40
(b) 50
(c) 60
(d) 75
Answer:

Option (d)

7.
According to IS 2026: Part_1, different testes performed are mainly classified into __________ categories.
(a) Two
(b) Four
(c) Six
(d) One
Answer:

Option (b)

8.
The tests done mainly on a prototype unit (any one unit) out of all manufactured units in a lot (same specification) is known as ___________ Test.
(a) Type
(b) Routine
(c) Special
(d) Commissioning
Answer:

Option (a)

9.
The tests done mainly on each and every unit out of all manufactured units in a lot is known as ___________ test.
(a) Type
(b) Routine
(c) Special
(d) Commissioning
Answer:

Option (b)

10.
If the tests are done as per _________ requirement to obtain special information useful to the user and specified in the tender is known as Special Test.
(a) customer
(b) manufacturer
(c) government
(d) High court
Answer:

Option (a)