11. |
Consider 100 MW, 50 Hz turbine generator has a speed regulation parameter R of 4 percent. How much will the turbine power increase if the frequency drops by 0.1 Hz with the speed changer setting unchanged?
|
||||||||
Answer:
Option (a) |
12. |
A 200 MVA alternator operates at no load at frequency of 50 Hz, it has an inertia constant of 5 MW-sec/MVA and the governing system has a time delay of 0.6 sec. If the load of 50 MW is suddenly applied then find the frequency deviation during this time?
|
||||||||
Answer:
Option (b) |
13. |
A 100 MVA alternator operating at full load at 50 Hz. H = 4 MWsec/MVA, Td = 0.5 sec. One of the transmission lines is tripped. So that output of the generator is reduced to 70 MW. Find the frequency deviation during this time?
|
||||||||
Answer:
Option (c) |
14. |
In which of the following frequency control method tie lines may be overloaded?
|
||||||||
Answer:
Option (a) |
15. |
The equation of area control error(ACE) is
|
||||||||
Answer:
Option (a) |
16. |
Power system network has a total power of 5000 MW at 50 Hz supplying to the different consumers. Frequency is varying at 1.5% per change of 2% load. Assume R =0.004 Hz/MW. Find the steady state frequency deviation if a sudden loss of 200 MW occur due to tripping of one of the transmission line?
|
||||||||
Answer:
Option (b) |
17. |
Load frequency and economic dispatch controller are working
|
||||||||
Answer:
Option (a) |
18. |
Economical dispatch controller has
|
||||||||
Answer:
Option (b) |
19. |
GRCs for which of the power plant is ignored
|
||||||||
Answer:
Option (a) |
20. |
The effect of speed governor dead band is that
|
||||||||
Answer:
Option (b) |