31. |
When WLSE method is applied for line flow only algorithm then the estimation of ‘x’ for power system is
|
||||||||
Answer:
Option (b) |
32. |
The solution of state estimation in power system is affected by
|
||||||||
Answer:
Option (d) |
33. |
The condition number for Gain Matrix ‘G’ is define as
|
||||||||
Answer:
Option (b) |
34. |
The Gain Matrix ‘G’ of power system becomes more ill-condition if the condition number is
|
||||||||
Answer:
Option (c) |
35. |
Power system is divided into ______sub-system to reduce computational burden in state estimation
|
||||||||
Answer:
Option (a) |
36. |
To derive external equivalency of power system, the subsystems are define as
|
||||||||
Answer:
Option (d) |
37. |
The method to find bad data detection is
|
||||||||
Answer:
Option (c) |
38. |
Identification of bad data is done by
|
||||||||
Answer:
Option (a) |
39. |
Suppression of bad data is done by selecting estimation index function as
|
||||||||
Answer:
Option (b) |
40. |
Network observability is define as
|
||||||||
Answer:
Option (c) |