Operation Research (3151910) MCQs

MCQs of Replacement Theory

Showing 21 to 28 out of 28 Questions
21.

In replacement analysis the maintenance cost is a function of

(a)

time

(b)

resale value

(c)

initial investment

(d)

none of these

Answer:

Option (a)

22.

Which of the following is the correct assumption for replacement policy when money value does not change with time?

(a)

No Capital cost

(b)

No scrap value

(c)

Constant scrap value

(d)

Zero maintenance cost

Answer:

Option (c)

23.

Which one of the following does not match the group?

(a)

Present Worth Factor (PWF)

(b)

Discounted rate (DR)

(c)

Depreciation value (DV)

(d)

Mortality Tables (MT)

Answer:

Option (d)

24.

Group replacement policy applies to

(a)

Irreparable items

(b)

Repairable items

(c)

Items that fail partially

(d)

Items that fail completely & suddenly

Answer:

Option (d)

25.

If a machine becomes old, then the failure rate expected will be

(a)

Constant

(b)

Increasing

(c)

decreasing

(d)

we cannot say

Answer:

Option (b)

26.

Replacement is said to be necessary if

(a)

Failure rate is increasing

(b)

Failure cost is increasing

(c)

Failure probability is increasing

(d)

Any of these

Answer:

Option (d)

27.

In this stage, the machine operates at highest efficiency and its production rate will be high

(a)

Infant stage

(b)

Youth stage

(c)

Old age

(d)

None of these

Answer:

Option (b)

28.

In retrogressive failures, the failure probability ......................... with time

(a)

increases

(b)

remains constant

(c)

decreases

(d)

none of these

Answer:

Option (c)

Showing 21 to 28 out of 28 Questions