Computer Aided Manufacturing (2171903) MCQs

MCQs of Integrated Production Management System

Showing 31 to 40 out of 46 Questions
31.

The first step in preparing an MPS is:

(a)

Develop a preliminary MRP

(b)

Check the preliminary MRP against available capacity

(c)

Resolve differences between the preliminary MPS and the capacity available

(d)

Develop a rough-cut capacity plan

Answer:

Option (a)

32.

Just-in-Time was successfully implemented by

(a)

Toyota

(b)

Honda

(c)

Suzuki

(d)

Volkswagen

Answer:

Option (a)

33.

In the Just-In-Time system

(a)

There is no delay

(b)

Conveyance times are balanced

(c)

Both of the given

(d)

All of the given

Answer:

Option (c)

34.

POK stands for

(a)

Product ordering Kanban

(b)

Process Ordering Kanban

(c)

Production Ordering Kanban

(d)

Plan Ordering Kanban

Answer:

Option (c)

35.

In Just-In-Time, the vendor is to be viewed by the company as a

(a)

Manager

(b)

Worker

(c)

Partner

(d)

None of the given

Answer:

Option (c)

36.

Just-In-Time is

(a)

Single unit production

(b)

Big lot size production

(c)

Both of the given

(d)

None of the given

Answer:

Option (a)

37.

MRP is different from JIT in terms of

(a)

Inventory

(b)

Quality

(c)

Human orientation

(d)

All of the given

Answer:

Option (d)

38.

The following is (are) the prerequisite(s) for JIT.

(a)

Multi-skilled workers

(b)

The vendor should produce defect-free

(c)

The worker should be empowered with his own decision

(d)

All of the given

Answer:

Option (d)

39.

Just-In-Time aimed at

(a)

Zero inventories

(b)

Reduced manpower

(c)

Over production

(d)

All of the given

Answer:

Option (a)

40.

Just-In-Time (JIT) combines the benefits of

(a)

Job order production and Line production

(b)

Batch production and Line production

(c)

Job order production and Batch production

(d)

None of the given

Answer:

Option (a)

Showing 31 to 40 out of 46 Questions