Computer Aided Manufacturing (2171903) MCQs

MCQs of Integrated Production Management System

Showing 1 to 10 out of 46 Questions
1.

Which of the following is not a part of Five M’s?

(a)

Material

(b)

Machine

(c)

Motion

(d)

Method

Answer:

Option (c)

2.

The correct sequence of operations in production planning and control is:

(a)

Routing-Scheduling-Dispatching-Follow up

(b)

Scheduling-Routing- Dispatching-Follow up

(c)

Dispatching-Routing-Scheduling- Follow up

(d)

Routing-Scheduling-Follow up-Dispatching

Answer:

Option (a)

3.

Which of the following is true for ‘Routing’?

(a)

It is the flow of work in the plant

(b)

Route sheets include a list of machine tools that are to be followed

(c)

It depends upon material handling facilities

(d)

All of the given

Answer:

Option (d)

4.

Loading may be defined as:

(a)

Sending the raw material to the machine

(b)

Sending the finished material to the store

(c)

Assign the work to the facilities

(d)

Uploading a software in the machine control panel

Answer:

Option (c)

5.

Dispatching authorizes the start of production operations by

  1. Release of material and components from stores to the first process
  2. Release of material from process to process
  3. Issue of drawings instruction sheets

Which of the following is (are) true?

(a)

Only i

(b)

Only ii

(c)

i & ii

(d)

i , ii & iii

Answer:

Option (d)

6.

The bill of material does not consist of

(a)

Part number

(b)

Specifications of part

(c)

Name of the part

(d)

Price of the part

Answer:

Option (d)

7.

The transit time consist of

(a)

Time is taken by raw material from machine to machine

(b)

Time consumed in moving the work between various departments

(c)

Time is taken by a worker to machine a component

(d)

None of the given

Answer:

Option (b)

8.

The master schedule is prepared for

(a)

Single product continuous production

(b)

Multi-product batch production

(c)

Assembly product continuous production

(d)

Single product batch production

Answer:

Option (c)

9.

Centralized and decentralized are the types of______.

(a)

Routing

(b)

Dispatching

(c)

Scheduling

(d)

Follow up

Answer:

Option (b)

10.

Predicting future sales activity is known as______.

(a)

Production planning

(b)

Process planning

(c)

Forecasting

(d)

Master scheduling

Answer:

Option (c)

Showing 1 to 10 out of 46 Questions