| 61. |
A machine that was supposed to run for 10 hours suffers a breakdown and runs only for 9 hours. Calculate availability.
|
||||||||
|
Answer:
Option (d) |
| 62. |
If the loading time is 400 minutes and downtime is 60 minutes, calculate availability.
|
||||||||
|
Answer:
Option (c) |
| 63. |
If the theoretical cycle time per unit is 0.5 minutes/unit, the number of units is 400, and the operating time is 400 minutes, calculate performance efficiency.
|
||||||||
|
Answer:
Option (d) |
| 64. |
If the overall equipment effectiveness is 40%, availability 82%, quality score 96%, calculate the performance efficiency?
|
||||||||
|
Answer:
Option (a) |
| 65. |
Which of the following is not an advantage of implementing TPM?
|
||||||||
|
Answer:
Option (d) |
| 66. |
What is not benchmarking?
|
||||||||
|
Answer:
Option (d) |
| 67. |
Benchmarking is used by organizations as a ________ tool.
|
||||||||
|
Answer:
Option (c) |
| 68. |
Company A manufactures 10 defective products on an average out of 1000 products manufactured. Company B manufactures 5 defective products on an average out of 1000 products manufactured. Which company must be chosen for benchmarking and by whom?
|
||||||||
|
Answer:
Option (b) |
| 69. |
Benchmarking involves ________ between the performance level of the organization with its benchmark.
|
||||||||
|
Answer:
Option (b) |
| 70. |
Benchmarking is used extensively in __________.
|
||||||||
|
Answer:
Option (c) |