Computer Aided Manufacturing (3161917) MCQs

MCQs of Integrated Production Management System

Showing 41 to 46 out of 46 Questions
41.

JIT does not believe in

(a)

Quality

(b)

Over production

(c)

Human relations

(d)

All of the given

Answer:

Option (b)

42.

Just-in-time production is also called

(a)

Kaizen

(b)

Lean manufacturing

(c)

Activity-based management

(d)

Backflush costing

Answer:

Option (b)

43.

Which one of the following is not an expected benefit of implementing a just-in-time (JIT) production system?

(a)

Lower total storage costs

(b)

Lower total setup costs

(c)

Lower manufacturing lead time

(d)

Lower total rework cost

Answer:

Option (b)

44.

Materials requirements planning (MRP) sometimes results in

(a)

Longer idle period

(b)

Less flexibility in responding to customers

(c)

Increased inventory carrying costs

(d)

Decreased setup costs

Answer:

Option (d)

45.

The manufacturing concept that relates demand forecasts to specific dates for completion is

(a)

Master production schedule

(b)

Materials requirements planning

(c)

Manufacturing resource planning

(d)

Bill of materials

Answer:

Option (a)

46.

Which of the following is not a goal of materials requirements planning?

(a)

Right part

(b)

Right quantity

(c)

Right customer

(d)

Right time

Answer:

Option (c)

Showing 41 to 46 out of 46 Questions