11.

for mass concrete works, the degree of workability should be 

(a)

low

(b)

medium 

(c)

high

(d)

very high

Answer:

Option (a)

12.

the capacity of a concrete mixer is expressed in terms of 

(a)

total volume of concrete produced per day 

(b)

total volume of concrete produced in 8 hours

(c)

total volume of concrete produced per hours 

(d)

volume of concrete mix handled per batch

Answer:

Option (d)

13.

which type of vibrator is generally used for compaction of concrete?

(a)

form vibrator 

(b)

needle vibrator

(c)

surface vibrator 

(d)

table vibrator 

Answer:

Option (b)

14.

surface vibrator is effected only when the thickness of concrete member does not exceed 

(a)

50 mm

(b)

200 mm

(c)

500 mm

(d)

800 mm

Answer:

Option (b)

15.

the water/cement ratio is expressed by 

(a)

volume 

(b)

weight

(c)

density 

(d)

none of the above 

Answer:

Option (b)

16.

the freshly prepared concrete mix should be consumed normally within 

(a)

24 hours 

(b)

8 hours 

(c)

1.5 hours

(d)

15 minutes

Answer:

Option (c)

17.

Separation of coarse aggregates from mortar during transportation, is known

(a)

bleeding

(b)

creeping

(c)

segregation

(d)

shrinkage

Answer:

Option (c)

18.

Sands of zone I are

(a)

coarse

(b)

medium 

(c)

medium to fine 

(d)

fine 

Answer:

Option (a)

19.

The size of fine aggregates does not exceed

(a)

2.75 mm

(b)

3 mm

(c)

3.75 mm

(d)

4.75 mm 

Answer:

Option (d)

20.

The main object of compaction of concrete, is:

(a)

to eliminate air holes

(b)

to achieve maximum density

(c)

to provide initimate contact between the concrete and embedded materials

(d)

all the above

Answer:

Option (d)