Construction Management (2180611) MCQs

MCQs of Project scheduling and Resource leveling

Showing 11 to 17 out of 17 Questions
11.
Resource levelling means 1. Economical utilization of resources. 2. Gradual increase in resources 3. Adjustment of resources to have the least variations 4. Complete revamping of resources to suit the requirements. 5. Validating network depending on resource constraints. Of these statements.
(a) 1 and 2 are correct
(b) 2, 3 and 4 are correct
(c) 3 and 5 are correct
(d) 1, 2, 3, 4 and 5 are correct
Answer:

Option (c)

12.
Which one of the following is the base for resource levelling?
(a) Delaying the completion of critical activities.
(b) Delaying the start of Non-critical activities.
(c) Reducing completion time of critical activities.
(d) Not delaying the completion of critical activities.
Answer:

Option (b)

13.
What is the process of incorporating changes and rescheduling or replanning called?
(a) Resource allocation
(b) Resource smoothing
(c) Resource levelling
(d) Updating
Answer:

Option (d)

14.
Updating may result in
(a) Change of critical path
(b) Decrease of project completion time
(c) Increase of project completion time
(d) All of the above
Answer:

Option (d)

15.
The time with which direct cost does not reduce with the increase in time is known as
(a) Crash Time
(b) Normal Time
(c) Optimistic Time
(d) Standard Time
Answer:

Option (b)

16.
The constraints in case of resource smoothening operation would be
(a) Resources
(b) Project duration time
(c) Both resources and project duration time
(d) None of the above
Answer:

Option (b)

17.
The time which results in the least possible construction cost of an activity, is known as
(a) Normal time
(b) Slow time
(c) Crash time
(d) Standard time
Answer:

Option (b)