Computer Aided Manufacturing (3161917) MCQs

MCQs of Integrated Production Management System

Showing 21 to 30 out of 46 Questions
21.

CRP takes material requirements from MRP and converts to

(a)

Standard hours of manpower

(b)

Standard hours of machine

(c)

Standard hours of load

(d)

All of the mentioned

Answer:

Option (d)

22.

Capacity planning is concerned with

(a)

How many machines required

(b)

How much labor required

(c)

All of the mentioned

(d)

None of the mentioned

Answer:

Option (c)

23.

CRP stands for:

(a)

Control Requirement Planning

(b)

Control Route Planning

(c)

Capacity Requirement Planning

(d)

Capacity Route Planning

Answer:

Option (c)

24.

MRP II stands for:

(a)

Material Requirement Planning

(b)

Material Resource Planning

(c)

Manufacturing Resource Planning

(d)

Manufacturing Requirement Planning

Answer:

Option (c)

25.

MRP-II system is called a closed-loop system because it considers

(a)

Inventory

(b)

Finance

(c)

Manpower

(d)

None of the mentioned

Answer:

Option (b)

26.

Purchasing and ___________ represent the implementation and control phase of the production planning and control system.

(a)

Material requirements planning (MRP)

(b)

Just-in-time (JIT)

(c)

Marketing

(d)

Production activity control (PAC)

Answer:

Option (d)

27.

The MRP forms a vital link between sales and production as follows:

(a)

The MRP makes possible valid order promises

(b)

The MRP is a contract between marketing and manufacturing

(c)

The MRP is a plan of what is to be produced and when

(d)

All of the given

Answer:

Option (d)

28.

PAC stands for:

(a)

Production active control

(b)

Production activity control

(c)

Procurement activity control

(d)

Procurement activity concept

Answer:

Option (b)

29.

The MRP forms a vital link between sales and production as follows:

(a)

The MRP makes possible valid order promises

(b)

The MRP is a contract between marketing and manufacturing

(c)

The MRP is a plan of what is to be produced and when

(d)

All of the given

Answer:

Option (d)

30.

The objectives in developing an MRP include:

(a)

To maintain the desired level of customer service by maintaining finished goods inventory levels or by scheduling to meet customer delivery requirements

(b)

To make the best use of material, labor, and equipment

(c)

To maintain inventory investment at the required levels

(d)

All of the given

Answer:

Option (d)

Showing 21 to 30 out of 46 Questions