21.

Which are the major risk in infrastructure projects?

(a)

Political Risks

(b)

Technological Risks

(c)

Economic Risks

(d)

All of the above

Answer:

Option (d)

22.

Which of the following is not a type of political risk?

(a)

Risk of Expropriation

(b)

Delays in permits and approvals

(c)

Construction delays

(d)

Contract Reneging

Answer:

Option (c)

23.

Which of the following is not a type of economic risk in infrastructure project?

(a)

Currency Devaluation

(b)

Community Protests

(c)

Inflation

(d)

Demand forecast errors

Answer:

Option (b)

24.

What is the full form of ADR?

(a)

Alteration Dispute Remedy

(b)

Alternative Dispute Resolution

(c)

Alternative Demand Supply

(d)

Alternative Dispute Ratio

Answer:

Option (b)

25.

Which of the following is not a type of Alternative Dispute Resolution?

(a)

Litigation

(b)

Arbitration

(c)

Conciliation

(d)

Mediation

Answer:

Option (a)

26.

Which method of ADR is mandatorily binding to both the parties?

(a)

Conciliation

(b)

Mediation

(c)

Arbitration

(d)

Negotiation

Answer:

Option (c)

27.

In which form of Alternative dispute resolution a middle person helps both parties to communicate and settle dispute themselves?

(a)

Arbitration

(b)

Mediation

(c)

Conciliation

(d)

Negotiation

Answer:

Option (b)

28.

Which of the following is less formal form of arbitration?

(a)

Litigation

(b)

Conciliation

(c)

Negotiation

(d)

Mediation

Answer:

Option (b)

29.

In which form of ADR there is no intervention of third party for dispute resolution?

(a)

Arbitration

(b)

Conciliation

(c)

Mediation

(d)

Negotiation

Answer:

Option (d)

30.

In which form of dispute resolution decision of tribunal is considered as binding to both the parties?

(a)

Arbitration

(b)

Litigation

(c)

Negotiation

(d)

Mediation

Answer:

Option (a)

Showing 21 to 30 out of 32 Questions