11. |
To protect project and stakeholders a special ________ is required.
|
||||||||
Answer:
Option (a) |
12. |
Goal of the stakeholder agreement is ________
|
||||||||
Answer:
Option (d) |
13. |
The key mistake often made while drafting an agreement is ________
|
||||||||
Answer:
Option (c) |
14. |
Detailed written agreement can avoid _________
|
||||||||
Answer:
Option (d) |
15. |
A project progress report should include ________
|
||||||||
Answer:
Option (d) |
16. |
A progress report does not include actual versus planned progress for ________
|
||||||||
Answer:
Option (c) |
17. |
A project progress report should not include ________
|
||||||||
Answer:
Option (b) |
18. |
Minimization of potential loss can be achieved by ________
|
||||||||
Answer:
Option (c) |
19. |
Which of the following is not a key benefit of contract risk management?
|
||||||||
Answer:
Option (a) |
20. |
Which of the following is key benefit of contract risk management?
|
||||||||
Answer:
Option (d) |