31. |
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
|
||||||||
Answer:
Option (a) |
32. |
The critical activity has
|
||||||||
Answer:
Option (c) |
33. |
Pick up the correct statement from the following
|
||||||||
Answer:
Option (d) |
34. |
Pick up the correct statement from the following
|
||||||||
Answer:
Option (d) |
35. |
PERT is
|
||||||||
Answer:
Option (d) |
36. |
In CPM analysis
|
||||||||
Answer:
Option (d) |
37. |
An event is indicated on the network by a number enclosed in
|
||||||||
Answer:
Option (d) |
38. |
While scheduling a project by CPM
|
||||||||
Answer:
Option (d) |
39. |
Pick up the correct statement from the following with regards to CPM network analysis of projects
|
||||||||
Answer:
Option (d) |
40. |
Pick up the correct statement from the following
|
||||||||
Answer:
Option (d) |