Which of the following statements is/are correct? 1. An activity is in between two node numbers, which need not be in an increasing order in the activity progress sequence. 2. The length of the arrow in a network has certain significance. 3. Concurrent activities are mutually independent and can possible be taken up simultaneously.
(a) 1 only
(b) 3 only
(c) 2 only
(d) 1, 2 and 3
Answer:

Option (b)

52.
Which one of the following is relevant to activity on Node (AON)?
(a) Dummy activities may be many
(b) There will be no dummy activities
(c) It is used for quite complex project
(d) It is easier to associate with time flow of activities
Answer:

Option (b)

53.
Which system of network given below completely eliminates the use of dummy activities?
(a) A-O-A (Activity-on-Arrow)
(b) A-O-N (Activity-on-Node)
(c) PERT
(d) CPM
Answer:

Option (b)