21. |
Critical path lies along the activities having total float
|
||||||||
Answer:
Option (c) |
22. |
Pick up the correct network
|
||||||||
Answer:
Option (b) |
23. |
The estimated time required to perform an activity, is known as
|
||||||||
Answer:
Option (c) |
24. |
If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
|
||||||||
Answer:
Option (d) |
25. |
Bar charts are suitable for
|
||||||||
Answer:
Option (a) |
26. |
The first method invented for planning projects, was
|
||||||||
Answer:
Option (a) |
27. |
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
|
||||||||
Answer:
Option (d) |
28. |
Pick up the correct statement from the following
|
||||||||
Answer:
Option (d) |
29. |
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
|
||||||||
Answer:
Option (a) |
30. |
Pick up the correct statement from the following
|
||||||||
Answer:
Option (d) |