| 1. |
Which one of the following represents an activity
|
||||||||
|
Answer:
Option (d) |
| 2. |
Pick up the incorrect statement from the following
|
||||||||
|
Answer:
Option (c) |
| 3. |
Pick up the PERT event from the following
|
||||||||
|
Answer:
Option (d) |
| 4. |
If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
|
||||||||
|
Answer:
Option (d) |
| 5. |
The performance of a specific task in CPM, is known
|
||||||||
|
Answer:
Option (c) |
| 6. |
Pick up the correct statement from the following
|
||||||||
|
Answer:
Option (d) |
| 7. |
A Milestone chart
|
||||||||
|
Answer:
Option (d) |
| 8. |
Completion of an activity on CPM network diagram, is generally known
|
||||||||
|
Answer:
Option (d) |
| 9. |
A dummy activity
|
||||||||
|
Answer:
Option (d) |
| 10. |
Pick up the incorrect statement from the following
|
||||||||
|
Answer:
Option (c) |